Our Process
-
Delivery to the site. Please advise on the maximum size of truck that can arrive on site.
-
Position the bases in the specified installation area within the building. Large bases will need to be craned; all others can go in the material hoist, subject to the base type.
-
Prepare the surface by removing concrete slag and installing the penetration stopper foam ring. Mark out the base position and place packers to ensure a level plane. Note: Penetrations need to be surveyed to ensure they are in the correct position.
-
Install the base.
-
Once the base is placed, pour grout to ensure the entire underside has complete contact.
-
Once the grout has dried, the base installation is fully completed. Note: Follow the drying time as specified on the grout Material Data Sheet.